Deep-technology work today needs computing that almost no student or early-stage team in Uttar Pradesh can reach. This project proposes 32 GPUs and 1.5 petabytes of storage in a purpose-built facility in Noida or Greater Noida, in Delhi NCR, run as a shared research resource.

Illustrative photo Peter Shanks / Wikimedia Commons, CC BY 2.0

At a glance

What
4 NVIDIA DGX H100 systems (32 GPUs) · ~1.5 PB storage · InfiniBand network
Building
A single-storey facility of about 1,800 sq ft
Where
Noida / Greater Noida (Delhi NCR) · site not yet chosen

From our charter

  • From our charter: artificial intelligence (Clause 3(a)(1))
  • From our charter: scientific research laboratories (Clause 3(a)(1))
  • From our charter: advanced embedded computing (Clause 3(a)(1))

Estimated cost

To build and run for one year: ₹32.09 crore – ₹42.69 crore

Capital
₹30.74 crore – ₹40.40 crore
First year of operation
₹1.25 crore – ₹2.04 crore
Refundable deposits
₹10.00 lakh – ₹25.00 lakh

These figures are estimates, made in October 2026 from the assumptions shown below. They become a funding target only after quotations are received and two of the foundation's administrators have approved them.

Estimated cost by sectionEach bar runs from the low estimate to the high one. The same figures are in the table.
Estimated cost by section
SectionLowHigh
ALand and site₹1.43 crore₹2.09 crore
BAI and data infrastructure₹21.50 crore₹27.50 crore
CPhysical infrastructure₹5.22 crore₹7.00 crore
DUtility connections₹0.28 crore₹0.53 crore
EPre-operative₹0.48 crore₹0.86 crore
FContingency₹1.82 crore₹2.42 crore
GFirst year of operation₹1.25 crore₹2.04 crore
HRefundable deposit₹0.10 crore₹0.25 crore

Figures in ₹ crore

See every line
CodeItemBasisLowHighSource
A1Land: ~465 m² (5,000 sq ft) industrial or institutional plot in Noida / Greater Noida (Delhi NCR), allotted or e-auctioned by the development authority on a long lease, zoning that permits a data centre465 m² × ₹27,560–₹39,580 (Noida Authority allotment rates for IT/ITES and data-centre land, 2025–26)₹1,28,15,400₹1,84,04,700Market rates
A2Stamp duty (7%) and registration fee (1%) on the lease premium8% of A1 (payable on the circle rate if it is higher)₹10,25,232₹14,72,376Uttar Pradesh rates
A3Title and allotment due diligence, survey, Noida / Greater Noida Authority allotment processing and building-plan approval, legalLump sum₹5,00,000₹10,00,000Estimate
B1AI supercomputer: 4× NVIDIA DGX H100 (32× H100), NVIDIA AI Enterprise, 3-yr supportThe foundation's own estimate₹16,00,00,000₹20,00,00,000The foundation's own estimate
B2Bulk storage cluster: 4 nodes, 2× CPU, 256 GB RAM, 12× 30.72 TB NVMe each (~1.5 PB raw)The foundation's own estimate₹2,50,00,000₹3,50,00,000The foundation's own estimate
B3Network fabric: Quantum-2 InfiniBand director switch, 2× 100GbE Arista, cablingThe foundation's own estimate₹3,00,00,000₹4,00,00,000The foundation's own estimate
C1Power and cooling: 300 kVA N+1 UPS, 400 kVA generator, redundant chillers, RDHx, pipingThe foundation's own estimate₹3,50,00,000₹4,50,00,000The foundation's own estimate
C2Site and civil works: 1,500–2,000 sq ft build-out, reinforced floor, racks, security, fire suppressionThe foundation's own estimate (priced at Gorakhpur rates)₹1,50,00,000₹2,00,00,000The foundation's own estimate
C3Delhi NCR adjustment to C2 (estimate was priced at Gorakhpur rates)15–25% of C2₹22,50,000₹50,00,000Estimate
D111 kV HT connection from the area's distribution company (PVVNL in Noida, NPCL in Greater Noida): 500 kVA transformer, HT/LT panels, cabling (excluding deposit)Lump sum₹25,00,000₹45,00,000Estimate
D2Two fibre links (two providers), last-mile buildLump sum₹3,00,000₹8,00,000Estimate
E1Data-centre architecture, MEP design, project managementLump sum (about 5–7% of C)₹30,00,000₹50,00,000Estimate
E2Fire NOC, building approvals, electrical inspectorateLump sum₹3,00,000₹6,00,000Estimate
E3Monitoring (DCIM), access control, NOC fit-out, critical sparesLump sum₹15,00,000₹30,00,000Estimate
F1Contingency on hardware (price and exchange-rate movement)5% of B₹1,07,50,000₹1,37,50,000Estimate
F2Contingency on land, works, utilities and pre-operative10% of A + C + D + E₹74,19,063₹1,04,77,708Estimate
G1ElectricityIT load 52.6 kW at 75–90% average use, PUE 1.35–1.6, ₹8–₹10 per kWh₹37,32,286₹66,35,174Estimate
G2Staff: HPC lead, 2 systems engineers, 4 shift technicians, 4 security guardsAnnual (cost to the foundation)₹55,00,000₹75,00,000Estimate
G3Internet: two 1 Gbps dedicated linksAnnual₹8,00,000₹15,00,000Estimate
G4Facility maintenance contracts: UPS, generator, chillers, fire systemAnnual₹6,00,000₹12,00,000Estimate
G5Insurance: equipment and building0.4–0.6% of B + C1 + C2₹10,60,000₹20,40,000Estimate
G6Generator diesel, consumables, administrationAnnual₹8,00,000₹15,00,000Estimate
H1Electricity security deposit (returned when the connection is surrendered)Estimate₹10,00,000₹25,00,000Estimate
Total₹32,08,51,981₹42,68,79,958

Concept plans

Concept floor plan
Concept floor planA single-storey building of about 1,800 sq ft: a 900 sq ft data hall with two rows of racks, a UPS and battery room, an electrical room, a corridor, a network operations room, a staging store and an entry with security.Data hall900 sq ft · reinforced slab · gas fire suppression · leak detection2× DGXRDHx2× DGXRDHxFutureRDHx-readyFutureStorage1.5 PBIB switchEthernetFutureService aisle(8 ft)Row A — computeRow B — storage and networkCDUFirecyl.UPS and battery300 kVA N+1 · 225 sq ftElectrical roomLT panel · PDUs · 225 sq ftCorridor · 4 ftNOC / control roommonitoring · 132 sq ftStagingand storeunboxing · sparesEntry andsecurityairlock · access controlMain entry60 ft30 ft30 ft data hallN08 ftConcept layout — not a construction drawingSite not yet chosen; the layout will be fitted to the real plot
Rooms and spaces
SpaceAreaWhat it is for
Data hall900 sq ftThe compute and storage racks, cooled by rear-door heat exchangers
UPS and battery225 sq ftUninterruptible power and batteries for the racks
Electrical room225 sq ftLow-tension panel and power distribution
NOC / control room132 sq ftMonitoring the cluster around the clock
Staging and store—Unboxing equipment and keeping spares
Entry and security—Airlock and access control
Concept site plan
Concept site planA plot of about 5,000 sq ft: the data centre building, a service yard with the transformer, the generator and two chillers, three parking spaces, a guard room and the gate onto the access road.Data centre building1,800 sq ft · see the floor planTransformer500 kVA · fencedGenerator 400 kVAacoustic enclosureChiller 1Chiller 2N+1Guard+ WCPPPGateAccess road~100 ft~50 ftN015 ftConcept layout — not a construction drawingSite not yet chosen; the layout will be fitted to the real plot
Rooms and spaces
SpaceAreaWhat it is for
Data centre building1,800 sq ftThe data centre itself — see the floor plan
Transformer—The 11 kV connection, fenced
Generator 400 kVA—Standby power, in an acoustic enclosure
Chiller 1—Two chillers, one a spare, for the rack cooling
Guard + WC—Guard room and toilet
Parking—Three parking spaces

View full size

What these estimates assume

  • Land: about 465 m² (5,000 sq ft) — room for the 1,800 sq ft building, a service yard for the transformer, the generator and the chillers, three parking spaces and a guard room. In Noida and Greater Noida, land for this use is allotted or e-auctioned by the development authority on a long lease, not bought freehold. Priced at the Noida Authority's 2025–26 allotment rates for IT/ITES and data-centre land in its Phases 2 and 3 (line A1); Greater Noida's 2025 industrial e-auction reserve prices fall inside that range. Zoning must permit the use.
  • Stamp duty and registration: 7% and 1% in Uttar Pradesh, which includes Noida and Greater Noida — charged on the lease premium, or on the circle rate if it is higher.
  • The foundation's own estimate for civil works was priced at Gorakhpur rates; line C3 adds 15–25% for building costs in Delhi NCR.
  • Electricity: an IT load of 52.6 kW at full draw, 75–90% average use and a PUE of 1.35–1.6 (line G1). Uttar Pradesh left its tariffs unchanged for 2026–27, and Greater Noida's supplier, NPCL, keeps a 10% discount; the tariff stays a working assumption until the distribution company confirms the category.
  • A 400 kVA supply needs a high-tension connection (line D1); its security deposit is refundable (line H1).
  • Hardware figures include GST and any import duty. If quotations come in before GST, about 18% would be added to lines B1–B3 and C1.
  • Staff: the minimum to run a GPU cluster around the clock — an HPC lead, 2 systems engineers, 4 shift technicians and 4 guards.

Not included

  • Hardware support after year 3.
  • Replacing the GPUs at the end of their life, typically after 4–6 years.
  • Scholarships, fellowships, training or incubation stipends for the people who will use the cluster.
  • Any income from compute time.

Where things stand

  1. ProposedDone
  2. Board resolutionNot yet
  3. Site chosenNot yet
  4. Quotations receivedNot yet
  5. Target approvedNot yet
  6. FundingNot yet
  7. BuildingNot yet

Delhi NCR AI Compute Centre